Doe Transmission Corridor Designations & Ferc Backstop Siting Authority: Has the Energy Policy Act of 2005 Succeeded in Stimulating the Development of New Transmission Facilities?

By Swanstrom, Debbie; Jolivert, Meredith M. | Energy Law Journal, July 1, 2009 | Go to article overview
Save to active project

Doe Transmission Corridor Designations & Ferc Backstop Siting Authority: Has the Energy Policy Act of 2005 Succeeded in Stimulating the Development of New Transmission Facilities?


Swanstrom, Debbie, Jolivert, Meredith M., Energy Law Journal


Synopsis: Historically, the Federal Energy Regulatory Commission (FERC) lacked authority over the siting of electric transmission lines. The FERC's siting role was limited to issuing certificates of public convenience and necessity for the construction of interstate natural gas transportation facilities. State agencies, in contrast, authorized the construction of electric transmission facilities. This regulatory landscape shifted, however, when the Energy Policy Act of 2005 (EP Act 2005) was enacted.

Recognizing the need for new transmission infrastructure in many areas of the country, the U.S. Congress established a four-part approach to the siting of new transmission facilities in congested areas. First, Congress directed the Secretary of the U.S. Department of Energy (DOE) to study transmission congestion. Second, based on the results of such study, Congress vested the Secretary of the DOE with authority to designate National Interest Electric Transmission Corridors (NIETCs). NIETCs are geographic areas experiencing transmission congestion that adversely affects consumers and wherein the relief of congestion would promote this country's energy independence, national security, and economic growth. Third, Congress allowed the states the opportunity to act first on applications for authority to site new transmission facilities within NIETCs. Fourth, Congress empowered the FERC with new backstop authority to site transmission lines within NIETCs under certain circumstances where, for example, a state fails to act quickly enough or imposes onerous conditions which effectively destroy the economic viability or benefits of a project.

Exercising its new authority, the DOE designated two, large NIETCs spanning several Southwestern and Mid-Atlantic States, which are now being challenged in Federal Court. The FERCs backstop siting regulations also were challenged, resulting in a Federal Court decision vacating those regulations in significant part. Moreover, the only utility to commence the process of seeking FERC backstop siting approval for a new transmission project has since announced that it no longer intends to pursue a FERC permit.

While the mere threat of potential federal preemption may have some influence on the siting behavior of states, by inducing them to approve more certificate applications at a faster pace or engage in greater regional cooperation, the provisions granting FERC siting authority in NIETCs do not appear to be a driving force for new transmission investments. Instead, other factors such as transmission rate incentives, authorized under Section 1241 of EP Act 2005, appear to have a much greater impact on the development of new transmission facilities. Since the adoption of the FERC's Final Rule on transmission rate incentives, the FERC has approved some form of rate incentives for over thirty transmission projects.

This article addresses recent legislative, regulatory, and litigation developments affecting the siting of transmission projects across the country, including remaining barriers to infrastructure development and actions being taken to overcome those barriers. We examine factors affecting the development of new transmission projects post-EPAct 2005, including the downturn in the U.S. economy, access to and the cost of capital, transmission rate incentives, the availability of federal grants or loans, the siting process, cost allocation disputes, renewable energy standards, reliability standards, and regional transmission planning.

Our research found that, despite the recent downturn in the U.S. economy, the number of applications filed with state commissions and the amount of investments made in transmission projects appear to have increased post-EPAct 2005. We also found that: (1) more applications appear to have been filed with state commissions for projects outside of NIETCs than for projects inside NIETCs; and (2) many state commissions acted on applications in approximately one year, both pre-and post-EPAct 2005.

The rest of this article is only available to active members of Questia

Sign up now for a free, 1-day trial and receive full access to:

  • Questia's entire collection
  • Automatic bibliography creation
  • More helpful research tools like notes, citations, and highlights
  • Ad-free environment

Already a member? Log in now.

Notes for this article

Add a new note
If you are trying to select text to create highlights or citations, remember that you must now click or tap on the first word, and then click or tap on the last word.
Loading One moment ...
Project items
Notes
Cite this article

Cited article

Style
Citations are available only to our active members.
Sign up now to cite pages or passages in MLA, APA and Chicago citation styles.

Cited article

Doe Transmission Corridor Designations & Ferc Backstop Siting Authority: Has the Energy Policy Act of 2005 Succeeded in Stimulating the Development of New Transmission Facilities?
Settings

Settings

Typeface
Text size Smaller Larger
Search within

Search within this article

Look up

Look up a word

  • Dictionary
  • Thesaurus
Please submit a word or phrase above.
Print this page

Print this page

Why can't I print more than one page at a time?

While we understand printed pages are helpful to our users, this limitation is necessary to help protect our publishers' copyrighted material and prevent its unlawful distribution. We are sorry for any inconvenience.
Full screen

matching results for page

Cited passage

Style
Citations are available only to our active members.
Sign up now to cite pages or passages in MLA, APA and Chicago citation styles.

Cited passage

Welcome to the new Questia Reader

The Questia Reader has been updated to provide you with an even better online reading experience.  It is now 100% Responsive, which means you can read our books and articles on any sized device you wish.  All of your favorite tools like notes, highlights, and citations are still here, but the way you select text has been updated to be easier to use, especially on touchscreen devices.  Here's how:

1. Click or tap the first word you want to select.
2. Click or tap the last word you want to select.

OK, got it!

Thanks for trying Questia!

Please continue trying out our research tools, but please note, full functionality is available only to our active members.

Your work will be lost once you leave this Web page.

For full access in an ad-free environment, sign up now for a FREE, 1-day trial.

Already a member? Log in now.

Are you sure you want to delete this highlight?