Newspaper article Pittsburgh Post-Gazette (Pittsburgh, PA)

Painters Run Road to Close Til August $2.35 Million Project Planned in Two Phases

Newspaper article Pittsburgh Post-Gazette (Pittsburgh, PA)

Painters Run Road to Close Til August $2.35 Million Project Planned in Two Phases

Article excerpt

Part of Painters Run Road in Upper St. Clair will be closed until August while crews build walls underneath it to stabilize the road.

The project, which began Monday, involves two sections of the road that will be closed separately. Workers from Carmen Paliotta Contracting of South Park will install I-beams every few feet with lagging walls between them to keep the road from sagging into Painters Run, said Jeanna Fisher, project manager and construction engineer for Allegheny County.

In the first phase, the road will be closed between McMillan Road and Robb Hollow Road. Crews will install a supporting wall 434 feet long and expect to finish by the end of May.

The second phase, between Essen Hill and McMillan, will involve 350 feet of supporting wall. The $2. …